12-07-2012, 09:31 AM
|
#11
|
|
Senior Member
Join Date: Jul 2002
Location: Rock Haven Lake - West Newfield, ME
Posts: 5,367
Thanks: 374
Thanked 1,057 Times in 495 Posts
|
From the Baysider
Quote:
Cell Tower Issue Appears Resolved
Planners
approve
amended
site plan BY TIM CROES Staff Writer ALTON — The Alton Planning
Board met for three
hours on Tuesday, Nov. 20,
and may have finally resolved
the cell phone tower
issue on East Side Drive.
A proposal was brought
forward by Industrial Communications
and Electronics,
Inc., Unicel and U.S. Cellular
to request for an amended
site plan to be able to secure
an alternative access to
the approved cell tower site
on property located on Bowman
Road.
The company requested
that a pair of waivers be approved
for the project pertaining
to landscaping and
the location of buildings,and
both these waivers were approved.
A letter was read into the
record from David Slade that
stated that he would not appeal
the decision of the Federal
Court ordering a tower
to be built at East Side Drive
at a height of 100 feet.
The board approved the amended site plan with several
conditions precedent and several subsequent conditions
|
Cost David Slade BIG BUCKS to fight this and appears that he lost?...or were concessions made?
|
|
|