			An example. Last year I had a shed installed on Welch Island in Gilford, between the 50’ and 150’ reference lines.  1st step apply for a permit from DES.  Without that permit it is a non-start.  Then apply for a permit in Gilford with the approved DES permit attached. Show that all Gilford zoning requirements are also met now that the DES permit is in hand. 
 Alan
 |