Whoever is doing the dock work will usually get the permit. Start now. The DES has some time controls on them, but they almost always send the application to the local Conservation Commission which has no such controls. Most CC's meet once a month and you may not get on the first month's agenda. Sometimes, they discuss and ask for changes or an in person site walk and you get continued to a second month.