View Single Post
Old 03-28-2008, 02:13 PM   #15
Onshore
Senior Member
 
Join Date: Apr 2004
Posts: 503
Thanks: 12
Thanked 425 Times in 146 Posts
Default

You could do that. The Department would want to see a construction sequence with timetables including the demolition of the old structure and would put condition the permit with a deadline for removal tied to the completion date of the new structure. The Department would also want to see planting plans for the restabilization of the old camp footprint after removal.
Onshore is offline   Reply With Quote